|
A uniform motorway
Work on the Northern Motorway Project (N1 Drogheda Bypass) running from
Gormanston in Co. Meath to Monasterboice in Co Louth began in April 2000
and is due for completion in the second quarter of 2003. The 21.5km motorway
was broken down into three separate contracts. John Loughran speaks with
Gary Curran, assistant project manager, with Uniform Construction, the
company that was awarded the contract to build 6.5 km of the motorway
from north of the Boyne just outside Drogheda.
 |
The Northern Motorway Project (N1 Drogheda Bypass) is one of the biggest
civil engineering projects undertaken in Ireland under the National Development
Plan. When completed the euro 240 million project will form a strategic
part of Euroroute EO1 which runs along the eastern seaboard, linking the
major international seaports of Larne, Dublin and Rosslare and the major
airports of Dublin and Belfast.
The motorway will significantly reduce journey times between Dublin and
Belfast, leading to savings in transport costs and will remove through
traffic from Drogheda and the village of Julianstown, having a beneficial
effect on noise and air pollution in the area.
|
Part
of the Uniform team, l/r: Declan Murphy, Aidan Gaynor, John
Duffy, Michael Duffy, Gary Curran, Philip Doherty
|
|
The new motorway will improve the quality of life for the communities
living in its hinterland, and will increase road safety for both commuters
and pedestrians alike.
Given the sheer enormity and scale of the project, it is little wonder
the National Roads Authority opted to divide the project into three separate
contracts - No.s 6,7 and 8.
Uniform Construction was awarded the section of the scheme referred as
Contract No.8 which included 6.5km of motorway and 4.5km of national roads
and side roads and the construction of eight bridge/underpasses north
of the Boyne.
 |
Uniform Construction mobilised its site team at the beginning of April
2000. The companys first task was to establish mobile site offices,
including services such as electricity, telephone, water supply and sewerage
connection. These site offices became the nerve centre of operations for
the duration of the project.
We then began a series of consultations with the landowners affected
by the route to address any concerns they had and to inform them of exactly
what were going to do. That process lasted for about two weeks.
However, our liaison officer was in daily contact with the landowners
throughout, Gary explained.
Utilising the services of a specialist contractor, the entire route was
then fenced off. On a project of this size we would use specialist
contractors in a number of areas. We employed the services of a specialist
fencing company because of the amount of fencing that had to be done,
he added.
It had been argued that the development of motorways and major road schemes
has robbed the country of many sites of archeological significance - Carrickmines
Castle on the site of the South Eastern Motorway being a case in point.
Gary explained that a team of archaeologists oversaw the next stage of
the project. When the fencing was completed the company began topsoil
stripping along the entire length of the route. A team of archaeologists
supervised this stage of the project. They watched every sod being turned
and identified areas of archeological interest. At one stage there was
a team of 55 archaeologists working on site.
At a cursory glance archaeology and road construction dont make
happy bedfellows. Their co-existence in terms of the project threw up
many challenges for Uniform Construction and indeed the archaeologists.
The biggest challenges we encountered were having to work around
the various archeological finds. The locations of the finds also threw
up challenges. There was a team of archaeologists working on the project
for the best part of a year and two months. However, that is part and
parcel of road construction in Ireland and we worked together to a common
goal.
The 6.5km of motorway was built to what is known in the trade as a cut
and fill design. That means excavating the hills and using
the material to fill the hollows. That reduces the amount of materials
that need to be imported for the project, Gary revealed.
Simultaneously, the company carried out pre-earthworks drainage.
If you are going to fill a hollow, you can create drainage problems
for the fields on either side. It is therefore important to drain these
areas before you fill them, Gary noted.
While the cut and fill team developed the course of the route,
a structures team was charged with the task of constructing
the various bridges and underpasses along the route. Gary commented: There
were eight structures on this project (over and under bridges). Ideally
you would like to get these structures started within two months of the
start of the project. These structures were constructed in tandem with
the earth works.
To make the most efficient use of the time available to complete the project
many activities are carried out simultaneously. To expedite the
amount of time available everything is condensed into the smallest possible
timeframe.
In general when we have about 1km of cut and fill completed,
we start importing the various categories of stone that are required for
the job. While other areas of cut and fill are ongoing, we are already
working on the completed areas. That includes drainage works and so on,
Gary elaborated.
While a project of this nature might seem a logistical nightmare to the
layman Gary explained that timing and planning is of the essence. The
whole project takes on a natural sequence of events, through planning
and timing. In general this project ran very smoothly.
It threw up a number of challenges, firstly because of its location
in relation to the Boyne and its possible archeological significance.
Secondly because it entailed the upgrading of 4.5km of national and secondary
roads and thirdly because of the increase in traffic in the Louth area
in the past few years.
All these factors had an impact on the project, but all-in-all we are
very happy.
At the peak of the project Uniform Construction employed a staff of 120
people as well as 80 sub-contractors. Gary is fulsome in his praise of
everybody associated with the scheme. He also recognises the efforts of
the consultants and resident engineer involved with the project.
The rapport that Uniform Construction developed with North Consult
and Kevin ORourke made a positive contribution to the project. We
had a very good working relationship in terms of lateral thinking and
problem solving and that needs to be acknowledged.
At the time of writing (mid-November) Gary was happy to report that Contract
No.8 was close to completion and will be opened in conjunction with Contract
No. 6 and No. 8 in the second quarter of next year.
|