|
Port Tunnel update
 |
A war of words has developed between Dublin City Council and the
Transport Umbrella Group, based at Dublin Port over the final operating
height of the Dublin Port Tunnel. John Loughran reports on the latest
exchanges.
The 4.5 km Dublin Port Tunnel, with an estimated price tag of £635
million is scheduled for completion in 2005. Designed to reduce
travel time for trucks from the M50 to Dublin Port, it will take
approximately 9,000 HGVs a day out of the capital.
The tunnel is being constructed with a physical height clearance
of 4.9 metres but will have an operational height clearance of 4.65
metres to protect loads and flapping tarpaulins, according to Dublin
City Council.
Since 1998 the Transport Umbrella Group has campaigned to have the
height restriction increased to cater for vehicles in excess of
the 4.65 metres, claiming that approximately 900 trucks per day
wont be able to use the tunnel. The lobby groups calls
have fallen on deaf ears.
Deputy City Engineer in charge of the project, Tim Brick recently
ruled out the possibility of increasing the height clearance, claiming
it would add another £130 million to the cost of the project
and reduce safety margins.
If we were to accommodate trucks with a height of 5.3 metres
(deck clearance on of the Irish Ferries vessel, Ulysses is 5.25
metres) it would involve dropping the floor by 700 to 750mm. This
would narrow lane widths which would inevitably reduce safety margins
in the tunnels enclosed environment, Mr Brick stated.
Mr Brick added that a three month survey of port related traffic
around the north port found that only 1.3 per cent of HGVs would
not fit in the tunnel. A similar survey of the south port terminal
is currently underway.
The National Roads Authority has specified a 5.3 metre clearance
on all over-bridges in its road programme, but Mr Brick insists
that this was intended to allow for resurfacing of the roads in
the years to come.
Mr Brick said that the British Governments policy favouring
high cube trailiers was out of kilter with
the rest of Europe and said they would find themselves confined
to the UK market.
He concluded by saying that neither the National Roads Authority
or the taxpayer would thank them for whacking on the extra
cost if the height restriction was increased. In any case,
nobody heard of 5.3 metre trucks when this project was designed.
Bricks comments have provoked ire from the Transport Umbrella
Group. Chairman Jerry Kiersey in a recent letter to the Irish
Times said: I am astounded at statements which he (Brick)
and others within Dublin City Council and the National Roads Authority
are putting on this issue.
He continued: Trucks 5.3 metres high do not exist here or
in the UK, nor have w e ever looked for them. We are seeking an
internal height which will allow trucks of 4.9 metres through. These
trucks are and have been a fact on our roads and those of our nearest
and biggest trading partner for the past 20 years.
The Transport Umbrella Group claims that Dublin City Council engineers
have highlighted tunnel heights in the UK built before the motorway
revolution in the 1950s in its efforts to justify the 4.65 metre
restriction at the Dublin Port Tunnel. They have ignored post
1950 tunnels such as the three on the M25 and others throughout
the UK, Mr Kiersey stated. He continued: I have direct
from the UK Highways Department, its guidelines on tunnel heights
which contradict Mr Bricks position.
Similarly, Dublin City Council engineers have highlighted tunnels
throughout the EU to support their case, while ignoring others such
as the EU-funded Oresund tunnel which links Denmark to Sweden, which
has an internal height of 6.1 metres and was completed in 2000.
The Transport Umbrella Group also disputes Dublin City Councils
claims that less than two per cent of port traffic will be unable
to use the tunnel. Indeed Dublin City Council seems unsure of the
validity of their own figures.
In December the Transport Umbrella group met with Dublins
Director of Traffic, Owen Keegan and Dublin City Councils
deputy engineer in charge of the project, Tim Brick. They
agreed to review the internal design of the tunnel to see if the
height of trucks able to use it could be increased from 4.65 metres
to 4.9 metres and also to conduct a new survey of all truck heights
monitoring all three access/excess points.
The Transport Umbrella Group believes that a height clearance of
4.9 metres would allow any truck capable of travelling by motorway
within Ireland and the UK to use the Dublin Port Tunnel. This
would seem a reasonable aim as the tunnels stated purpose
is to carry trucks to and from the port to the M50, Kiersey
stated.
He added: If this does not happen an alternative route will
have to be designated for taller trucks and this route will inevitably
become a rat-run for all trucks seeking to avoid paying tolls at
the Westlink.
However, Dublin City Council is of a different opinion. The councils
website categorically states: It has been suggested that over
height HGVs will have unrestricted access to the citys road
network, thereby undermining one of the fundamental objectives of
the Dublin Port Tunnel, the removal of port HGV traffic from the
citys road network.
It is important to state that over height HGVs will have only
limited alternative surface access available to them. A city wide
HGV management strategy will be introduced to accompany the opening
of the Dublin Port Tunnel. This will place severe restrictions on
when and where HGVs will be permitted to operate within the city.
We can only wait on the results of Dublin City Councils new
survey of port traffic to determine exactly how many trucks per
day wont fit in the tunnel. The Transport Umbrella Group is
confident the figure will far exceed the 2 per cent figure currently
doing the rounds.
|