Irish Trucker logo
 

 


SearchTrucker



 

Cashel’s bottleneck blues

Limerick based civil engineering and construction company Roadbridge began building the N8 Cashel bypass in Co Tipperary in 2003, which has an estimated price tag of £29.5 million. Project engineer Pat McCarthy gave Irish Trucker an insight into the complexities of the project.

Coming along nicely

The N8 Cashel bypass and the accompanying N74 Link Road is the first phase of the new N8 between Portlaoise and Watergrasshil in Co Cork. The long-awaited bypass, which will greatly relieve traffic congestion in a town renowned as a notorious traffic bottleneck extends for a distance of 7 km from the townland of Knocksaintlour on the south side of the town to Garryard on the north.

The N74 Link Road extends for a distance of 2km from the townland of Windmill at its junction with the existing N8 to the townland of Horeabbey at its junction with the N74.

The new N8 bypass will be constructed to dual-carriageway specifications and will include two wide paved carriageways, hard shoulders, wide grass margins and a wide median. The N74 Link Road will be a single carriageway consisting of two lanes, two hard shoulders and two grass margins.

Bridging the gap

The new N8, which will include three over-bridges and one under bridge will take an estimated 7,200 vehicles out of the town of Cashel on a daily basis. The new route, which was funded by the National Roads Authority under the auspices of the Department of Transport, the National Development Plan and the European Union's Regional Development Fund will take two years to complete.

Roadbridge, formerly known as Pat Mulcair Civil Engineering has a proud tradition in road construction. In the recent past the company has been involved in notable road schemes such as the Kildare, Bunratty, Limerick and Portlaoise bypasses. So it wasn't surprising when the company was awarded the contract for the N8 Cashel bypass.

Pat commented: "Pat Mulcair Civil Engineering had been involved in roadworks for the best part of 30 years, before it became a limited company four years ago and changed its name to Roadbridge. The company has a proven track record in this area, and we were all delighted when we were awarded the contract."

At the height of the project some 200 people will be employed

The company moved onto site in May 2003. Having set up its site offices, Roadbridge fenced off the entire length of the bypass. "Once we fenced off the site, we began top soil stripping, which was overseen by a team of archaeologists on behalf of the National Roads Authority."

By their very nature heavy earth moving equipment and archaeologists don't make happy bedfellows. However, Pat fully recognises the importance of the archaelogists' contribution in protecting the country's heritage.

He commented on the challenges this can throw up for the company: "It depends from contract to contract. If they find anything of significance it can cause delays. However, they have an important job to do, so with a little planning you can normally work around it."

In advance of the tendering process the company conducted site investigations to determine the quality of the material along the route of the bypass, so Roadbridge had a pretty good idea what it was likely to encounter.

"We carried out site investigations before tendering because this was a design and build project. We needed to know the quality and quantity of the materials along the course of the route so we could factor that in to our tender,' he elaborated.

The project is due for completion in 2005

As previously mentioned, the bypass will include three-over bridges and an under-bridge. "We try to construct the road as far the bridge so that we can gets trucks in and out. Each bridge will take about seven months to complete so we need to start them early in the contract," he revealed.

On completion of the 'cut and fill' process, the company will begin raising the level of the road with filling. "The job is planned so that the rock excavated from the cut and fill is crushed on site to produce what is known as a 'catting layer'. That is then covered with clause 804 which is a finer material. That is graded to the required levels and tolerances," Pat added.

Each project throws up its own unique challenges. In this respect the N8 Cashel bypass wasn't exceptional. "The drainage of this project threw up some challenges to our design team. The rock excavation also posed challenges. In the latter stages of the project, the rock will have to be blasted," he revealed.

At the height of the project some 200 people and a veritable host of plant and equipment will be employed on the project. Roadbridge will also utilise specialist contractors in a number of areas such as rock blasting and tarmac laying.

Hundreds of thousands of tonnes of earth and rock will be moved in the process before the road begins to take shape. Thousands of motorists will look on in anticipation and frustration as they try to negotiate the notorious bottleneck that is Cashel.

However, all good things come to those who wait. The road will finally begin to resemble a dual-carriageway when the tarmac is laid, crash barriers erected and road markings put in place.

If the project runs to schedule it will be open to the public in the middle of 2005, some two years after the official sod was turned. Long after the official opening, the benefits of the N8 Cashel bypass will be felt by thousands of motorists for generations to come.

Pat and all the team at Roadbridge will be justifiably proud.


© 2009 Lynn Publications. All Rights Reserved.