|
Dundalk Western bypass nears completion
The Celtic Roads Group was awarded the contract to design, construct,
finance, operate and maintain for a concession period of 30 years, the
M1 Dundalk Western bypass. Construction manager Ian Cunningham is confident
the route will be completed ahead of its February 2006 completion date.
|
The
route will form an integral part of the
M1 corridor
|
|
The M1 Dundalk Western bypass will form an integral part of the M1 corridor
from Dublin to the Border, when it opens in spring 2006. The Celtic Roads
Group would consider this project to be a demonstration of what effective
partnership can achieve for the delivery of the National Development Plan.
Currently the motorway terminates south of Dundalk, and all traffic must
pass through the town with resultant delays and congestion difficulties.
The new 12 km stretch of road, which stretches from Haynestown to Ballymascanlon,
will reduce travel times by up to 30 minutes at peak times.
Under the terms of the public / private partnership, the Celtic Roads
Group comprising HBG Ascon Ltd, NTR PLC, Edmund Nuttal Ltd and Dragados
Consesiones de Infraestructuras SA, a major Spanish firm will construct
the 12kms of motorway, along with approximately 7km of new link roads,
12 over / under bridges and a major railway bridge.
In addition the consortium will take over the operation and maintenance
of 43km of existing motorway from Haynestown to Gormanston, including
the recently constructed Boyne Bridge and adjacent toll plaza for a 30-year
period.
As part of the deal the consortium also took over the operation of the
toll plaza adjacent to Drogheda. We also had to upgrade the toll
plaza to include dedicated electronic non-stop toll collection lanes as
part of the contract, Ian confirmed.
The project commenced in early February 2004 when the consortium signed
the contracts, for what is only the second major inter-urban Public /
Private Partnership scheme awarded under the National Development Plan
2000 - 2006.
The concession runs for 30 years from February 5, 2004 when the
contracts were signed. The completion date for the construction is February
11, 2006, but we hope to open ahead of schedule, Ian enthused.
 |
Advanced archaeological works had been carried out prior to the awarding
of the contract. This allowed the consortium to begin ground clearance
within a matter of days of signing the contract. Because of ecological
factors we had to have the site cleared before the end of March. We would
be talking about removing hedges and so on, he added.
Topsoil stripping was quickly followed by what is known in the trade as
cut and fill. Basically it means cutting out material
in one location and moving it to another. There were a number of rock
areas, which we exposed at an early stage to give us a head start. We
extracted a large amount of rock from an area adjacent to the Armagh road.
That rock was later used in the construction of the road pavement,
Ian explained.
As with all civil engineering projects, the M1 Dundalk Western bypass
threw up certain challenges for contractors. None more so than the construction
of a railway bridge on the Dublin to Belfast line.
There were 14 structures along the motorway - 10 road bridges, two
river bridges, one pedestrian under pass and a railway bridge. The railway
bridge posed the biggest challenge, Ian confirmed.
Using a technique known as Autoripage, the bridge was constructed some
40 metres from its final resting place, before being slid into position.
The technique is commonly used across Europe, although this was
the first time it was used in Ireland, he added.
The bridge, which weighed in at7,500 tonnes and took 25,000 man-hours
to build was slid into position over the Easter Bank Holiday Weekend,
following an operation that was planned with military precision.
After Iarnrod Eireann removed the existing rail tracks, the excavation
of the embankment commenced at 00.01 hours on March 24th and continued
for 20 hours by which time some 23,000 cubic metres of material had been
removed.
Using some of the biggest excavators in the country it took almost
20 hours to remove the embankment. It was a difficult operation, but it
went very smoothly nonetheless.
The excavation was carried out by two CAT 365 excavators, a CAT 385 excavator,
supported by two track excavators and a dozen Volvo A40 dumps trucks to
haul away the material.
Ian elaborated: The technique is complicated to explain but simple
in its principle. The bridge was built on a base slab, which in turn sits
on a guide raft. Cables from the back of the bridge in the base slab run
along channels to a point below the ground where they are anchored to
the guide raft. By pulling on the cable the bridge moves forward and slides
into place.
In total the bridge travelled 44 metres to its final position, supporting
the Dublin to Belfast railway line. The Autoripage technique was
chosen because we could only shut the Dublin to Belfast line for a short
period of time. The line was closed for 72 hours over the Easter Weekend.
The line reopened on Easter Monday, Ian affirmed.
While it only took 72 hours to slide the bridge into place, its construction
took somewhat longer. We started constructing the bridge before
Christmas. The bridge weighed 7,500 tonnes and took a lot of man-hours
to construct, he noted.
While construction of the motorway began at the southern end construction
work didnt follow a straight line. We would have opened up
several fronts at the same time. Its not like building a house where
you start at the bottom and finish at the top, he elaborated.
He continued: Civil engineering allows you the opportunity to work
on several areas at the same time in and ordered and timely fashion.
Once the cut and fill is complete the contractors then proceed
to lay a capping layer. The purpose of the capping layer
is to provide a platform for the construction of the road paving. We are
using a gravel that is graded from five inches down. Some of that material
was produced on site, while the rest was imported from local suppliers,
he affirmed.
A layer known as CBM is then placed on top of the capping layer. CBM
stands for cement bound material. It isnt widely used in Ireland.
We processed the rock found on site and batched it with the cement on
site. The whole process was contained on site, Ian explained.
Once the CBM layer is complete drainage, dressing and the final layers
of bitumous will be addressed before the final layers of bituminous pavement
are laid. After that stage you would be approaching completion and
road signs and safety barriers would be put in place. One of the final
jobs is putting down the road markings, he revealed.
Throughout the project the main contractors Ascon and Dragados call on
the services of specialist contractors. You would have the likes
of the earthworks contractor the pre-cast concrete suppliers, concrete
suppliers, gravel suppliers as well as the likes of the Swiss company
that pushed the bridge into place, Ian affirmed.
Subject to the vagaries of the Irish weather Ian is confident the project
will be completed ahead of schedule.
The 12km route, which will form part of the Trans European Road Network
(Euroroute E101), will edge the M1 motorway ever closer to the Border,
will significantly reduce journey times and make an important contribution
towards road safety.
|