M50 upgrade making good progress
Traffic congestion in Dublin will be greatly reduced with the completion
of the first phase of the M50 upgrade in March 2008. Garrett Doyle of
lead contractor SIAC/Ferrovial Joint Venture explains more.
 |
The first phase of the M50 upgrade is on target to be completed by early
March which is good news for hauliers and motorists alike who can expect
significant time savings as a result of the improvements.
Works commenced on the countrys busiest motorway between the N4
and Ballymount interchanges in May 2006 and has been progressing at a
steady pace. The multi-million euro scheme involves adding a third lane
in each direction of the M50 over a distance of 31km between the M1 and
Sandyford interchanges, and will eventually double the motorways
capacity.
Were on course to have Phase 1 completed by the beginning
of March, explains Garrett Doyle, who is a project manager with
lead contractors SIAC/Ferrovial.
The upgrade will greatly reduce journey times and the route will
be a lot safer as well. Over the course of the upgrade, a lot of time
and effort has gone into traffic management schemes. In this regard, we
have liased with South Dublin County Council, Dublin Corporation, NRA
National Toll Roads and the Gardai.
The upgrade project, which is being undertaken in three phases, involves
construction works/widening of the M50 from two to three lanes in each
direction (with a fourth auxiliary lane between some junctions) from south
of the M50/M1 interchange near Dublin Airport through to the Sandyford
interchange with the upgrade of 10 junctions along this length. The total
cost of the upgrade is approximately EUR1 billion with Phase 1 being funded
by the Irish Exchequer under the National Development Plan (2000-2006),
while Phase 2 is being delivered through the PPP (Public Private Partnership)
mechanism.
 |
Phase 1 comprises the widening of almost 8km of carriageway between the
N4 (Galway Road), N7 (Naas Road/Red Cow Roundabout) and Ballymount interchanges.
The N4 interchange will become a full free flowing interchange. The interchange
is grade separated with the M50 mainline passing underneath. Four new
road bridges and one new pedestrian/cyclist bridge are being constructed.
One existing pedestrian bridge will be reconstructed as a pedestrian/cyclist
bridge.
The N7 interchange will become a partial free flowing interchange. The
interchange is also grade separated with the M50 mainline passing underneath.
The two existing bridges from the roundabout will be used and a further
three new road bridges and two pedestrian/cyclist bridges are being constructed.
The Ballymount interchange involved the provision of a further signalised
interchange with existing roundabouts removed. Free flow slip lanes are
being provided for left turning traffic. The existing bridge is being
upgraded to three lanes and one additional two-lane road bridge is being
constructed to the north of the existing road bridge.
Phase 2, which will commence later this year, comprises the widening of
24km of the M50 from south of the M1/M50 Turnapin interchange to the N3
interchange, and from south of the Ballymount interchange to the Sandyford
interchange, including the upgrade of interchanges along these sections.
 |
Phase 3 will comprise the widening of 1.3km length of motorway south
of the N3 interchange to north of the M50 West-Link toll plaza. A crucial
element of the M50 upgrade will be the introduction of barrier free tolling
next autumn. The contract for the construction of barrier-free tolling
on the M50 has been awarded to BetEire Flow. The entire project is due
to be completed in 2010.
Given their wealth of experience in road construction, the awarding of
the design and build contract to SIAC/Ferrovial Joint Venture came as
no real surprise. SIAC is a long-established Irish construction firm,
while Spanish company Ferrovial Agroman is one of Europes leading
specialists in the design, construction, financing, maintenance and management
of infrastructural projects.
The two companies have struck up an excellent working relationship in
recent years and are also currently working on the M3 Clonee to North
of Kells project. This project consists of 60km of new motorway together
with a further 50km of associated side roads and other roads. A total
of 135 new structures will be required with two toll plazas and associated
control buildings.
SIAC/Ferrovial were also the lead contractors on the M4 Kilcock-Kinnegad
project which was completed 10 months ahead of schedule in 2006, and the
A1/N1 cross border Newry-Dundalk link road which was made possible by
the Good Friday Agreement.
Founded in 1913, SIAC's business has grown through its reputation for
delivering quality projects that always meet and often exceed its clients'
expectations. This philosophy continues to drive SIACs business
and the company is now one of Irelands largest contractors, and
has also built up a strong reputation in the UK. Through a programme of
alliances with major international civil engineering contractors and specialist
contractors, SIAC is able to undertake multidisciplinary projects of scale
and complexity.
The M50 project poses particular traffic management challenges as the
joint contractors are required to construct the works with up to 100,000
vehicles per day traversing the site. As one of the most high-profile
road projects to be undertaken in the State, the management of relations
with the public and multiple stakeholders will be a key factor in the
success of the project.
The site team is led by Mario Mostoles (project manager, Ferrovial) and
John Glynn (construction manager, SIAC). Mario has worked in Ireland for
the past two years where he was a section manager on the M4 Kilcock-Kinnegad
project, while John transferred back to Dublin from the N15 scheme in
Donegal.
The project is divided into four principal sections, with one each managed
by Garrett Doyle and Declan Battle of SIAC, and Joaquin Losada and David
Fanjul of Ferrovial. Over 400 are employed on the project, including direct
employees of SIAC and Ferrovial, and sub-contractors.
As already stated, the capacity of the M50 will double when the upgrade
is completed. Free flowing interchanges will mean fewer roundabouts and
traffic lights so traffic will move faster through junctions. In addition
to three lands of traffic in each direction, there will be a fourth lane
linking major junctions, i.e. motorists entering the M50 and the N7 and
exiting at the N4 will only be able to stay on a dedicated fourth lane
between these two interchanges and will not need to move out onto the
M50 proper.